BP/Maersk look outside industry to develop HPHT drilling technology

By Astrid Wynne, contributing editor

A main challenge in Maersk’s project with BP will be to create a full package for HPHT, particularly with well control, Maersk Drilling chief technical officer Frederik Smidth said. A main challenge in Maersk’s project with BP will be to create a full package for HPHT, particularly with well control, Maersk Drilling chief technical officer Frederik Smidth said.

A partnership between BP and Maersk Drilling to develop conceptual engineering designs for HPHT drilling technology is looking beyond industry norms. “Higher pressure can be taken care of with more steel, to put it in simple terms, but the high temperatures have implications on the seal technology within the risers, the material technology inside the BOP and the rams to take the high temperatures. That’s where we might have to look a little bit outside our industry for solutions,” Frederik Smidth, chief technical officer at Maersk Drilling, told Drilling Contractor.

As the project is just beginning – the two companies announced their partnership agreement in February – much still needs to be explored. However, Mr Smidth said he already sees that one major challenge will be to create a reliable package for HPHT, even if certain technology components are already available. Major vendors, for example, have development of 20,000-psi well control equipment and driller risers under way.

“I see the main challenge is to get the full well control package safe and efficient to operate. We will need a hookload capacity beyond the current 2.5 million lbs for these types of wells, but the challenge is finding the well control and lifting structure equipment and the flexible hoses and connections used in the drilling system.”

Under Maersk’s agreement with BP, the initial studies will outline the basic design criteria, such as hookload capacity and the vessel size and type that will be capable of operating in a 20,000-psi and 350?F environment, as well as the safety systems needed to protect and train crews. Phase 1 of the project is expected to last approximately one year, with a potential extension into a contract for a finalized design that could culminate in an order by late 2015 or early 2016.

“The first units would begin drilling the US Gulf of Mexico (GOM) in 2018 or 2019, with possible additional requirements in Egypt and Azerbaijan if a contract is awarded,” Mr Smidth said.

He added that this joint project with BP is also providing Maersk Drilling with valuable insight into the deepwater cost structure from an operator’s perspective. Knowledge found within BP’s deepwater well database, for example, is helping Maersk to design systems to reduce nonproductive time.

“The total cost of drilling a deepwater well in the US GOM is around $1.2 to $1.3 million a day. We, as the drilling company, account for only 50% of the costs for an oil company,” Mr Smidth explained. “It is interesting to understand the other half of those costs, like for example the 30% to 40% nonproductive time when drilling deepwater wells. We expect to gain a knowledge that can be used in more traditional rig designs. The aim of the process is to build rigs which are safer, faster and cheaper to operate.”

Going forward, Mr Smidth sees the potential for more collaborative technical projects between drilling contractors and oil companies. “For the new frontiers – 20k, Arctic Sea, Barent Sea, the high H2S drilling in the northern Caspian – I think this kind of cooperation is essential. Drilling costs are increasing, and we can only reduce them by understanding each other’s cost structure.”


View the original article here

Wednesday, May 29, 2013

ASTM subcommittee to develop hydraulic fracturing standards

By Katie Mazerov, contributing editor

ASTM International has formed a subcommittee to develop standards for hydraulic fracturing. Subcommittee D18.26, which held its first meeting in January, includes 230 volunteer members from operating companies, service companies, geotechnical and geo-environmental firms and regulators, said Robert Morgan, director of technical committee operations for ASTM. Member companies include BP, Chevron, Chesapeake Energy, Schlumberger and Halliburton.

The committee has identified several areas of focus:

• Site investigation;

• Site construction;

• Permitting;

• Drilling;

• Fracturing and stimulation;

• Drilling fluid characteristics;

• Waste management of completion fluid;

• Site monitoring and well abandonment; and

• Cementing and grouting.

The standards are strictly voluntary. Once they are developed, they will be ASTM standards that can be used in the marketplace and potentially cited in federal regulations, which currently reference some 2,500 standards.

“One of the reasons ASTM has been so successful is that it gets industry involved in the process and brings the regulatory community to the table to develop standards everyone can live with,” Mr Morgan said. “The process allows industry to be proactive rather than have a governmental entity determine what the standards should be. ASTM is an open and transparent organization, and anyone who has an interest in the process can get involved.”

The subcommittee, formed after an exploratory task force reached out to industry stakeholders, also works closely with related organizations to avoid duplicative efforts. One of the first endeavors of the task force was to review existing API documents related to hydraulic fracturing. “If another organization is meeting a marketplace need, ASTM typically does not get involved,” Mr Morgan noted. “We looked for voids in the API documents where ASTM standards could supplement the work that has already been done.

“Another objective in this effort is that ASTM does not want it to come across as an environmental watchdog activity but rather as a way to make the practice of hydraulic fracturing safe and efficient,” he continued. For example, one issue discussed at the initial meeting was proppant shape, which can make a significant difference in keeping fractures open for better flow of hydrocarbons.

The standards development process could potentially take more than a year, depending on the complexity of the topics being addressed. “The process depends on the urgency of the needs the members have identified,” Mr Morgan said. “The ASTM process has a proven history, and one of the reasons it has lasted so long is because of the professionals involved. This is a level playing field where everyone has an equal say.”

For more information on how to get involved in Subcommittee D18.26, please visit www.astm.org/COMMIT/D1826.htm.