Monday, March 26, 2012

Reservoir drives choice of RSS vs mud motors

Rotary steerables suit narrow formations; mud motors may be more cost-effective in broader boundaries


By Eric Malcore, Weatherford International Ltd


The ratio of directionally drilled wells to vertically placed wells is increasing. Access to progressively harder to reach reserves is driving more complex well geometries, which predicate the use of rotary steerable systems (RSS) to enhance rate of penetration (ROP), improve borehole quality and reduce torque and drag and stick slip. The various RSS technologies available today have revolutionized the drilling process in horizontal and deviated wells by facilitating greater intermediate reaches and longer laterals, allowing casing to be run more easily and allow proper weight transfer.


The service industry estimates that RSS technologies account for approximately $3.5 billion of the estimated $15 billion directional drilling market. The dynamics are shifting in favor of RSS.


Although not a new technology, high-performance mud motors also have become an accepted and reliable method in directional drilling operations, in many cases providing a cost-effective alternative to more costly rotary steerable tools.


Knowing when to choose a rotary steerable system and when to use a high-performance mud motor is critically important to optimize the drilling project from both an engineering performance and a cost perspective.


Many horizontal or deviated wells are extremely difficult or impossible to drill without an RSS. A key benefit of RSS technology is that it directs well trajectory without sliding, a condition that impacts the stability and orientation of the drill string to rotate in one direction. Without proper rotation, the entire drill string can stick to the borehole wall, making it difficult to achieve the desired weight transfer to the bit to achieve planned penetration rates. RSS tools provide continuous rotation of the drill pipe, minimizing the risk of the pipe becoming stuck or buckling.


Sliding also creates more waste because the lack of rotation keeps the fluid in a static state, making it more difficult to remove cuttings. The cuttings then pack off around the bottomhole assembly, causing the drill string to stick. With the continuous rotation enabled by rotary steerable tools, however, the friction holds the cuttings in suspension, allowing the fluid to create a vortex around the drill string to provide consistent hole-cleaning.


RSS technology also reduces drag, allowing extension in well reach, especially important in horizontal applications. Rotary steerables typically deliver a smooth in-gauge wellbore and control the toolface at the bit, which provides more accurate directional control and less tortuosity. They also enable the use of logging-while-drilling (LWD) azimuthal sensors to obtain full borehole images.


Applying Precise Directional Control


An important factor in rotary steerable systems is that they provide precise directional control and are therefore suited to narrow zones as tight as 1 ½ ft. In that regard, the tools also can provide geosteering in these narrow reservoirs, where corrections can be made in real time without sliding.


An RSS was used to successfully drill and complete a section of a horizontal water-injection well with an 8 ½-in. hole in Abu Dhabi.


Using Weatherford’s Revolution rotary steerable system, the operator was able to drill 2,200 ft (671 meters) at a depth of 8,725 to 12,918 ft (2,659 to 3,937 meters) in less than 90 hrs in one run, saving 41 hrs of drilling time and achieving a significant cost savings without nonproductive time.


The same system was used in another Abu Dhabi water-injection well to facilitate drilling and completion of an ultra-narrow, 6-ft zone with a 6-in. hole size and a run length of 4,193 ft (1,278 meters).


The operator was able to drill almost 20 ft (6 meters) deeper than anticipated, reaching a target that otherwise would have been missed.


In an onshore Saudi Arabian field prone to lost circulation, differential sticking and hydrogen-sulfide challenges, the same technology drilled a 3°/100-ft (30-meter) dogleg section with a 6 1/8-in. hole in an extended-reach horizontal water-injection well to a target depth of 16,856 ft (5,138 meters). Average ROP was 35 ft/hr (11 meters/hr). Prior to deployment of the system, optimal ROP had been difficult to achieve with a steerable motor assembly.


The system drilled a total of 7,316 ft (2,230 meters) in one run, achieving a field run-length record and meeting the operator’s goal to minimize excess tripping time. The operation saved 24 hours in drilling time and associated costs and allowed the operator to avoid stuck-pipe and lost-in-hole risks that occur in similar extended-reach wells.


In the Bay of Bengal in Eastern India, the same RSS technology performed a record-breaking shoe-to-shoe run in a claystone formation, with interbedded sandstone, marl and calcareous clay. The deep exploratory well had an inclination of 34°. The system drilled a 12 ¼-in. in-gauge hole and then drilled to a measured depth of 4,918 ft (1,499 meters) to improve the average ROP and reduce the number of wiper trips and backreaming. Drilling time was 192 hrs, with an average ROP of 25.6 ft/hr (7.8 meters/hr).


RSS technology has been enhanced in recent years by the development of motorized rotary steerable systems, where a power section placed on the RSS tool provides additional rpm and torque while still achieving the benefits of control and eliminated sliding. This hybrid-type application is increasingly being used in regions such as the Middle East, where the rock and carbonates are especially hard.

High-performance mud motors can save 50% or more a day over rotary steerable systems. Mud motors also can be used with smaller rigs that can’t rotate fast enough to enable the rotary steerable mechanism to perform. However, rotary steerables provide greater precision in directional control, an advantage in tight formations.


High-performance Alternative


Despite its many benefits, rotary steerable technologies can present some disadvantages, including cost, if used in situations where precise directional control is not the primary objective. For example, to justify the expense of using a rotary steerable system, the savings in rig time and other costs must be greater than the rotary steerable cost.


Rotary steerable drilling performance is delivered from the use of surface rotation, making them rig-dependent. They offer limited selection of bit sizes and speeds, and they involve greater complexities, both mechanically and electronically compared with motors. The high rotation speeds can cause premature wear to the casing and drill string, which can be slightly decoupled by using an integrated power section with the RSS, albeit adding significantly to the cost.


The replacement cost of a rotary steerable system, if it is lost in the hole, can exceed $1 million, depending on the system and size. That does not include the replacement cost of the accessory tools.


In cases where deploying an RSS is either cost-prohibitive or impractical, a high-performance mud motor can also achieve desired results, provided it is used in the proper application. However, high-performance mud motors are best suited to broad target areas and zones that require less precision, or in doglegs that are too aggressive for an RSS.


Used since the early 1990s for a multitude of oilfield applications, high-performance mud motors achieve greater torque and ROP than conventional mud motors. The mud motor leverages the reduced rubber profile in the power section to gain additional torque, which creates less deformation as the rotor spins. The reduced rubber deformation translates into more torque for the bit, which in turn allows for higher ROP and more aggressive bit designs.


For operators, the key advantage is that a high-performance mud motor can result in daily cost savings of 50% or more over an RSS. Lost-in-hole costs also are significantly lower; a 6 ¾-in. high-performance mud motor has a typical lost-in-hole cost of $168,000.


High-performance mud motors can often out-perform standard, non-motorized RSS, which depend on the rig rotary table to spin the bit. The motor power component of the high-performance mud motor, on the other hand, provides bit rotation and power directly to the bit. High-performance mud motors also can be used in situations that involve smaller rigs that can’t rotate fast enough to enable the rotary steerable mechanism to perform.


Another benefit is that all bit types and sizes can be used with a high-performance mud motor, making it useful for a variety of applications, including situations where a particular bit that is not compatible with an RSS must be run.


High-performance mud motors do, however, require sliding for directional control, which typically reduces ROP. They offer poor and inconsistent hole-cleaning and poor hole gauge. Also, LWD sensors often get pushed back farther from the bit. Motor bend with high-performance mud motors can limit the drill string rotary speed or not allow any rotation at all. These factors must be considered in selecting this method of drilling.

It’s believed that rotary steerable technologies account for approximately $3.5 billion of the estimated $15 billion directional drilling market.


UAE Test Cases


High-performance mud motors have been used successfully in many deviated drilling operations and have achieved better-than-average ROP rates in three offshore test cases – the Thamama, Hith and Arab formations in the United Arab Emirates.


Seven wells in the Thamama Formation featured multiple target zones and were characterized by hard, Cretaceous limestone, but they presented no sliding issues. The operator used high-performance mud motors to drill the wells, which were not horizontal but had deviations ranging from 0° to 30° and had 8 ½-in. hole sizes.


The high-performance mud motors performed with an average ROP of 28 ft/hr (8.5 meters/hr). The best performance for the motors was 44 ft/hr (143.4 meters/hr), and the worst performance was 17 ft /hr (5.2 meters/hr). The Hith Formation also featured hard drilling conditions, with Jurassic anhydrite and dolomite rock but no sliding issues. The operator again drilled seven hole sections, all deviated but not horizontal, with 8 ½-in. hole sizes and a build section of 25° to 90°. In this case, the high-performance mud motors delivered an average ROP of 18 ft/hr (5.5 meters/hr). The highest ROP was 41 ft/hr (12.5 meters/hr), and the lowest was 9.88 ft/hr (3 meters/hr).


In the Arab Formation, featuring Jurassic carbonate/anhydrite rock, both sliding and directional control challenges were present. The lateral section was +/- 90°. Again, the operator drilled seven 8 ½-in. hole sections with high-performance mud motors.


The operation achieved an average ROP of 18 ft/hr (5.5 meters/hr). The best performance was 31 ft/hr (9.4 meters/hr), while the worst performance was 10 ft/hr (3 meters/hr).


The emergence of multiple technologies to optimize the drilling process can make selection of the proper technology confusing. Understanding reservoir properties along with diligent analysis of the well program, including formation, bit selection, directional program and other factors, must be considered when determining whether an RSS or a high-performance mud motor will achieve the best results in terms of cost and efficiency.


In tight or narrow formations where precise, directional control is needed, RSS are often the optimal choice for achieving drilling optimization and increased ROP. In zones with broader boundaries, a high-performance mud motor can provide results at a lower cost, provided issues such as sliding are carefully examined.


Revolution rotary steerable system is a trademark of Weatherford.


View the original article here

Case study: Algerian underground blowout

Incident demonstrates need for well-trained crews, adequate mud equipment


By Pedro Martinez Aguilar, Repsol Exploration; Michael Arnold, John Lee, Boots & Coots, a Halliburton Service

Partial mud-loss in the Tournasian formation occurred because the formation permeability and porosity were sufficiently high to allow loss of whole mud. An open-hole formation integrity test (FIT) should be performed after repairing the loss zone and regaining circulation to ensure the wellbore pressure integrity is still equivalent to the FIT recorded at the last shoe depth.


The outcome of a well control and blowout incident reflects how well a crew is trained and prepared. This article will discuss the sequence of a well control operation that occurred in Algeria in December 2008, which includes the influx, steps to identify the situation, operations to control the underground blowout and the response of the well.


An operator drilled a 12 1/4-in. exploratory well at 11,516 ft in the Emsian formation and set a string of 13 3/8-in. casing at 5,250 ft. A pit gain was observed, and the well was shut in. The maximum annulus pressure recorded after shut-in was 570 psi. A sudden drop in annulus pressure to 325 psi suggested lost circulation and was assumed to be in the Tournasian formation (5,305 ft to 6,180 ft), where severe lost returns had been recorded while drilling (5,580 ft to 5,740 ft).


The pressure drop made it difficult to assess the kick, thus hindering conventional well-control techniques.


Initial Well-Control Actions


Pore-pressure equivalent mud weight (EMW) at the Emsian formation was estimated to be 11.7 to 12.7 lbm/gal. The formation-strength EMW at the Tournasian formation was estimated to be 10.0 to 11.7 lbm/gal. Believing the well was experiencing losses to the Tournasian, 189 bbl of 11.6-lbm/gal mud was pumped into the casing annulus. The annulus pressure remained constant, indicating the possibility of an underground blowout.


As the annulus pressure continued to increase to 1,000 psi, 340 bbl of 11.6-lbm/gal mud was pumped down the casing annulus to reduce the pressure. A volume of 340 bbl of 9.9-lbm/gal mud was pumped down the drill string while maintaining a maximum choke-back pressure of 1,600 psi. After pumping the mud, the stabilized pressure was used to determine the bottomhole pressure. While adjusting the choke, an influx entered the wellbore.


To prevent the annulus pressure from increasing beyond 1,000 psi, batches of 13.3-lbm/gal mud were pumped periodically into the annulus. The initial volumes of mud contained lost-circulation material (LCM) to help cure the losses.


The drill pipe was filled periodically to avoid gas migration up the drill string. Shut-in drill pressure remained at 0 psi. Losses in the annulus were reduced when the LCM reached the loss zone, and the shut-in drill pipe pressure gauge began indicating pressure.


Sandwich-Kill Attempt


The hole was displaced through both the drill pipe and the annulus, “sandwiching” the influx into the lost zone.


The Emsian formation pressure was predicted to be between 12.1 and 12.7 lbm/gal EMW, meaning a 15.9-lbm/gal kill mud would overbalance the Emsian formation by +/- 3.2 lbm/gal. A cement unit was used to pump 818 bbl of 11.6-lbm/gal mud down the casing annulus, and rig pumps were used to pump 1,006 bbl of 15.9-lbm/gal mud down the drill pipe.


The operation was partially successful because the annulus pressure was still 600 psi at the end of the procedure. However, it confirmed that the bottomhole pressure and the pressure at the loss zone were higher than predicted.


Casing pressure began to increase, and drill pipe pressure remained at 0 psi. Once the casing pressure reached 2,050 psi, the drill pipe pressure increased proportionally to the casing pressure.


Communication between the annulus and the drill string was demonstrated by bleeding off 300 psi on the casing, causing a 25-psi drill pipe-pressure decrease. To keep the casing pressure as low as possible, gas was bled from the casing annulus until fluid was observed at the surface. Thereafter, the casing pressure could not be further reduced.


Circulation-Kill Attempt


Heavy mud was pumped down the drill string to control bottomhole pressure and to circulate gas out of the well. Without an accurate value for the bottomhole pressure, the proposed kill-mud weight was 13.3 lbm/gal, based on the mud hydrostatic pressure and the shut-in casing pressure but neglecting the height of the gas in the annulus.


After pumping began, drill pipe pressure dropped to 0 psi. Consequently, the choke had to be adjusted without a reference value for drill pipe pressure. The choke position was kept constant, adjusted only when annulus pressure increased. Mud losses were difficult to quantify, and the well was shut in when the rig ran out of mud.


During the mud buildup, temperature and pressure logs were run to the depth of the downhole motor in the bottomhole assembly. These logs indicated the fluid level was around 4,216 ft and the pressure at 11,411 ft total depth was 4,630 psi.


The temperature log detected disturbance around 5,600 ft, which corresponded to the depth of the Tournasian formation. The log response was interpreted as fluid movement. The repeat section of the log corroborated the crossflow at the Tournasian formation at the same depth where losses were experienced in drilling.


Annulus-Pressure-Control Attempt


Because drill pipe pressure was 0 psi, there was no reference for operating the choke. It was decided to maintain constant annulus pressure or allow it to decrease. Four LCM pills were pumped. As the first pill reached the thief zone, the losses decreased to zero. Subsequently, the pit levels increased, indicating slight gains. The volume pumped and the time when the LCM reached the surface indicated the hole was in gauge.


Once the losses were reduced to a minimum, the pump rate was increased and the choke was opened slightly to counteract the vacuum effect on the drill pipe. However, the mud level in the drill pipe dropped continuously.


When the choke opened to 1/16 in., casing pressure dropped more than expected. This jeopardized the control of the influx from the Emsian formation. The pumps were stopped, and after a few minutes, the drill pipe pressure began to increase. An influx of gas appeared to migrate inside the string, prompting the pipe to be displaced with 13.3-lbm/gal mud.


The well response indicated gas remained in the annulus, and the integrity of the Tournasian formation was still low. The kill operation resumed, and 239 bbl of 12.1-lbm/gal mud were pumped ahead of the 13.3-lbm/gal mud. The 12.1-lbm/gal mud did not reach the Tournasian formation. Consequently, the pressure in front of the weak zone at the Tournasian formation was minimized. At that point, more LCM pills were pumped.


While making repairs to the mud-gas separator, additional influxes entered the wellbore. When pumping restarted, pressure peaks suggested partial plugging of the ports in the circulation sub. As a precaution, no further LCM was pumped.

The drilling log reflects the sequence of events of an underground blowout and the well control operations that occurred in Algeria in December 2008.


Low-Choke Attempt


Changes in the annulus pressure after shutting in the well indicated that there was still a small amount of gas in the annulus or at least above the Tournasian formation. The “low-choke” method was used, attempting to control the influx from the kick zone at the bottom of the well while allowing the loss zone to deplete to a lower pressure. The basis was to hold the choke pressure equal to or slightly greater than the last recorded shut-in value while circulating as fast as safely possible. The mud density was designed to sufficiently overbalance the kick zone.


An 11.6-lbm/gal mud provided 50-psi hydrostatic pressure, in addition to annulus friction-pressure overbalance to the kick zone. The choke pressure was calculated using the casing pressure observed at the beginning of the operation, with an additional 200-psi safety factor added. The circulating rate used was as fast as the surface equipment would allow. Sixty-three bbl of 12.2-lbm/gal mud were pumped into the annulus.


An increase in drill pipe pressure suggested the presence of gas inside the pipe. The operation was stopped when bottoms-up volumes from the Tournasian and the Emsian formations were observed at the surface, and the crew prepared to reduce the annulus pressure. Operations resumed after the drill pipe was filled.


The well was monitored, and the casing pressure was bled off 100 psi to test communication between the annulus and the drill pipe. An unexpected 200-psi increase in drill pipe pressure occurred, indicating there were now two different pressure systems partially isolated by one or more packoffs in the annulus.


Once the bottoms-up volume from the Emsian formation reached surface, the choke was opened at separate intervals to bleed off 200 psi. Four intervals were needed to reduce the casing pressure to 500 psi. Because it was difficult to keep the casing pressure stable, it was decided to fully open the choke, allowing the casing pressure to rapidly bleed off to 0 psi. No returns were recorded at surface.


The pump rate was increased without result, except for a brief increase in pipe pressure, which suggested a restriction or packoff was present in the annulus. A total of 110 bbl of mud, along with 60 bbl of water, was pumped down the annulus to compensate for the fluid-level drop. The calculated fluid level was 1,371 ft.


Once pumping into the annulus stopped and the casing pressure dropped to 0 psi, the blowout preventer was opened to monitor the well. Because of the possibility of pipe plugging and annulus packoff, the pipe was worked. Five feet of pipe movement was gained, but rotation was impossible. The well was shut in with the annular preventer when mud overflowed at the bell nipple.


An attempt was made to establish circulation. Initially, the casing pressure rose very quickly to more than 3,000 psi. On the second attempt, the drill pipe pressure increased from 1,800 psi to 3,500 psi after pumping only 31 bbl of mud. With an entire drill pipe capacity of 187 bbl, this indicated the pipe was plugged. Further, the casing pressure did not reflect the pressure changes. It was concluded that one or more packoffs were present in the annulus.


An unsuccessful attempt was made to break the packoffs by pumping down the annulus. Subsequent efforts focused on bleeding off the annulus pressure and attempting to work the pipe to free the drill string, and a “lubricate and bleed” method was attempted. Large amounts of gas were recorded at surface, resulting in the annulus pressure dropping to 0 psi, and losses were also recorded. After filling up the hole with 13.3-lbm/gal mud and water, the well again began to flow. A 50-bbl mud cap using a 13.3-lbm/gal high-viscosity pill was pumped down the annulus but was unsuccessful in preventing gas from percolating to the surface.


When the annulus was bled off and the mud level was confirmed to be at surface, the pipe was worked. The drill string was torqued-up and continued to be worked. The string did not become free, moving 8 ft upward without releasing any torque.


The pipe was completely stuck, and circulation was impossible. The operator abandoned the drilled section of the well. The inside of the drill string was killed by isolating the inside diameter with cement or mechanical plugs. The drill string was perforated as deeply as possible to isolate the annulus using cement. A coiled-tubing unit was then used to cut the drill string, and the Tournasian formation was allowed to unload.


Lessons Learned


• The Tournasian partial mud-loss event occurred because the formation permeability and porosity were high to allow loss of whole mud (natural losses). This was evident by treating the losses with LCM. It is recommended that an open-hole formation integrity test (FIT) be performed after repairing the loss zone and regaining circulation. This helps ensure the wellbore pressure integrity is equivalent to the FIT recorded at the last shoe depth.


• If leak-off occurs before the equivalent shoe FIT is reached, wellbore maximum allowable surface pressure and kick tolerance should be recalculated at the loss-zone depth to accommodate the downgraded FIT.


• If creditable formation-pressure data is not available, the heaviest kill-mud weight possible should be used.


• Training in kick detection and BOP shut-in on all rigs is recommended.


The main lesson learned from this incident was the necessity for well-trained and experienced drilling crews and the importance of adequately sized mud-mixing and handling equipment.


The authors thank the management of Repsol Exploration and Boots & Coots for permission to present this paper.


This article is based on a presentation at the 2011 IADC Critical Issues Asia Pacific Conference & Exhibition, 23-24 November, Kuala Lumpur, Malaysia.


View the original article here

News Cuttings


Justin Hodges awarded for committee leadership


 Joe Hurt (right), IADC regional vice president North America and lead staff land/HSE, presents Justin Hodges (left), director of safety, claims &  risk at Hodges Trucking, with the IADC Committee Chairman’s plaque for leading the Rig Moving Committee from 2010 through 2011. Mr Hodges’ successor is Anthony Zacniewski, director of HSE at Bandera Drilling.


Geer named IADC regional director – ME & Africa


Dave Geer has joined IADC as regional director for the Middle East & Africa, responsible for coordinating and promoting the IADC’s activities in those regions.


Mr Geer has more than 34 years of experience in the drilling industry, including 15-plus years working offshore in several positions and 19 years in management positions in sales, project management and marine operations.


He has expertise in MODU operations, risk management, safety and loss control, regulations and contracts.


View the original article here

OOC awards recognize IADC SEMS work

Two IADC staff members were among 10 people who received recognition awards from the Offshore Operators Committee (OOC) on 7 December 2011 in recognition of their efforts and contributions in the development and rollout of the SEMS Toolkit last year. Thr

The Offshore Operators Committee recognized major contributors to the SEMS Toolkit on 7 December. Front row from left are Brenda Kelly and Julia Swindle, IADC; Milton Bell, ExxonMobil; and Bill Walker, Cobalt International Energy. Back row from left are Troy Nugent, Baker Hughes; Greg Duncan, ConocoPhillips; and Jeff Ostmeyer, Anadarko.


ough an OOC task force and in cooperation with the Center for Offshore Safety (COS), the toolkit was developed to address consistency and compliance with new requirements by the US Bureau of Ocean Energy Management (BOEM), as well as their effective networking with other industry representatives.


IADC’s Dr Brenda Kelly, senior director of accreditation and certification, and Julia Swindle, industry compliance specialist, attended the ceremony to receive the awards from OOC chairperson Susan Hathcock, Anadarko Petroleum.


Dr Kelly’s contributions were her leadership of the Competence Subcommittee, development of the Knowledge and Skills Documentation Tool, contributions to the SEMS Compliance Readiness Worksheet and other tools, and speaking at a series of rollout conferences held in August and September last year. Ms Swindle contributed to review of all tools and provided administrative support of the entire SEMS Toolkit development effort. IADC has seconded Ms Swindle to work with the COS for one year to help with the initial establishment of the COS.


Besides Dr Kelly and Ms Swindle, other recipients of the award included Milton Bell, ExxonMobil; Greg Duncan, ConocoPhillips; Roger Molaison, BHP Billiton; Troy Nugent, Baker Hughes; Jeff Ostmeyer, Anadarko; Kim Parker, Hercules Offshore; Ruth Rodriguez, Delmar; and Bill Walker, Cobalt International Energy. Each recipient contributed significantly to the development of the tools in the toolkit, working with subcommittees and/or providing administrative support. A significant number of IADC member companies also contributed to the effort.


“The participants on the task force have my sincerest gratitude and respect for their leadership and contributions to the SEMS toolkit, which is of immeasurable value to our industry,” said Mr Ostmeyer, who led the toolkit development effort.


Currently, the OOC SEMS Subcommittee and its task groups have concluded their work with the public release of 8 SEMS Toolkit products. Tools developed were:


• Audit checklist;


• Contractor readiness tool;


• Matrix of regulatory required training for drilling, production and marine positions;


• SEMS orientation curriculum;


• Knowledge and skills documentation tool;


• Operator-contractor agree letter templates; and


• Definitions.


These tools are available on the IADC website.


The COS will adopt all tools and maintain them going forward, although a small team from the OOC SEMS Subcommittee continues to work with the COS in the development of the Auditor Certification Program.


View the original article here

Hendricks to lead Patterson-UTI upon Wall’s retirement


William Andrew Hendricks Jr will join Patterson-UTI Energy as chief operating officer on 2 April, the company announced today. Mr Hendricks comes from Schlumberger, where he has served since 2010 as president of the Drilling and Measurements division. In addition, Patterson-UTI announced that Doug Wall, president and chief executive officer, will retire later this year. It is expected that Mr Hendricks will assume the position of president and chief executive officer upon Mr Wall’s retirement.


“Andy’s vast experience successfully managing diverse businesses – businesses with technology and geographic challenges – demonstrate his ability to lead and manage. We believe this experience and leadership ability make him the right person to help us execute our current strategic plan of continuing to grow our two core businesses – land drilling and pressure pumping in North America,” Mark Siegel, Patterson-UTI chairman, said.


He said of Mr Wall’s retirement: “We greatly appreciate the excellent leadership that he has provided; during his tenure, our company has made enormous strides. Our APEX rig programs, which numbered six rigs when he arrived, now stand at 94 new APEX rigs. Within our overall fleet of approximately 330 marketable rigs, we now have approximately 150 that are highly capable of drilling shale and other unconventional plays. Moreover, during his tenure, we have more than quadrupled our pressure pumping fleet and significantly expanded the geographic footprint of our pressure pumping business.


Mr Wall will continue as CEO until his retirement later in the year and will remain as a consultant for two years to ensure a smooth transition


Mr Hendricks received a bachelor of science degree in petroleum engineering from Texas A&M University in 1987. He also completed executive finance training at IMD in Switzerland in 2008. Mr Hendricks started his career working for Ocean Drilling and Exploration Company as a roustabout and roughneck on the Ocean Spur jackup in the Gulf of Mexico.


Click here to watch IADC group VP/publisher Mike Killalea talk with Andy Hendricks at the 2012 IADC/SPE Drilling Conference in San Diego to discuss recently launched technologies.


View the original article here

Sunday, March 25, 2012

Tubular fracturing: Pinpointing the cause

Improper heat treatment can trigger temper embrittlement in oilfield tubulars  


By Srinivasa Koneti, Samit Gokhale, Thomas Wadsworth, T.H. Hill Associates

Figure 1 (left): Intergranular cracking, characterized by triple points, rock-candy or a faceted appearance, occurs at and along the grain boundaries of metal. Figure 2 (right): Transgranular cracking occurs through or across the crystals or metal grains and is characterized by cleavage steps, river patterns, feather markings and tongues. This shows an example of a transgranular fracture on the fracture surface of low-carbon steels.


Brittle fracture of oilfield tubular components can occur due to the material having low fracture toughness – such material often presents low Charpy V-notch (CVN) impact energy values – or from exposure of the material under load to certain corrosive operating environments. A brittle fracture can show characteristics of transgranular or intergranular cracking when analyzed through a scanning electron microscope (SEM).


Intergranular cracking is the cracking or fracture that occurs at and along the grain boundaries of a metal. It is characterized by triple points, rock-candy or a faceted appearance when the fracture is analyzed through SEM. Figure 1 shows a typical example of an intergranular fracture on the fracture surface of low carbon steels.


Transgranular cracking is the cracking or fracture that occurs through or across the crystals or metal grains. It is characterized by cleavage steps, river patterns, feather markings and tongues when the fracture is analyzed through a SEM. Figure 2 shows a typical example of a transgranular fracture on the fracture surface of low-carbon steels.


Intergranular cracking is often the mode of fracture that occurs when tubular components are exposed to environmental conditions that contain aqueous H2S. Such failures promulgate the notion that detection of intergranular cracking morphology on fracture surfaces is confirmation of failure through sulfide stress cracking (SSC) or hydrogen embrittlement, even when no evidence exists for exposure to H2S or a source of nascent hydrogen.


Study of intergranular cracking related failures has shown that such failures can occur not only when the component is exposed to nascent hydrogen but can also be caused by temper embrittlement of the material resulting from improper heat treatment.


Temper embrittlement typically occurs when carbon or low-alloy steels are held at or slowly cooled through the temperature range of 375°C (705°F) to 575°C (1,065°F) during the tempering process. If the steels are tempered or slowly cooled at these temperatures, the material shows brittle characteristics (loss of impact toughness).


Steels that have experienced temper embrittlement can be restored to their original or expected toughness by heating (tempering) to 600°C (1,100°F) or above, followed by rapid cooling to below approximately 300°C (570°F).The fracture surface of a material with low CVN impact energy values (brittle material) would normally show transgranular signatures when analyzed under a SEM, whereas a ductile material affected by environmental attack, such as hydrogen embrittlement, shows intergranular separation at grain boundaries.


However, brittle fracture of a material that undergoes temper embrittlement also shows signs of intergranular cracking. Examination of the fracture surface of a component that has undergone temper embrittlement can present intergranular or mixed mode of intergranular and transgranular fracture morphology.

n Case 1 from South Texas, the pin connection of a new saver sub failed. The drilling engineer recognized the failure as a brittle failure.


Case studies of Temper Embrittlement Failure


Case 1 – South Texas, onshore US


In March 2009, while making up the pin connection (6 5/8-in. reg) of a saver sub, the pin connection on the sub failed. The operator reported that the saver sub was procured new and was in service for three days before the failure occurred.


Based on the appearance of the fracture surface, the proximate cause of the failure was readily recognized by the drilling engineer as a brittle failure. To confirm the failure mechanism, the failed sub was sent for failure investigation.

In Case 2 from Oklahoma, the pin connection twisted off while making up the pin connection of a saver sub.


Case 2 – East Oklahoma, onshore US


In May 2010, while making up the pin connection (6 5/8-in. reg) of a saver


sub, the pin connection twisted off. Based on the fracture surface morphology, the failure mechanism was identified as a brittle fracture with rapid crack propagation. To confirm the cause of the failure, the failed sub was sent for further investigation.


Case 3 – Northeast Trinidad, offshore


In April 2010, the operator was in the final stage of drilling a horizontal well that entailed the pullback of the 36-in. production pipeline. While pulling back drill pipe joint No. 90, a 7 5/8-in. reg pin connection on a sub that fastened the 42-in. hole-opener to the 500-ton swivel failed downhole.

In Case 3 from Northeast Trinidad (lower left), a pin connection on a sub that fastened the hole-opener to the swivel failed downhole.


The attached fractured sub was pulled out, and the mating portion of the sub was not recovered by fishing and subsequently resulted in losing the well. Based on the appearance of the fracture surface, the proximate cause of the failure was identified as fatigue, followed by a brittle fracture. To confirm the failure mechanism, the failed sub was sent for investigation.


Metallurgical Analysis of Failed Subs


Metallurgical analysis of the fractured pin connections on the subs was performed to identify the cause of the failure and the factors that contributed to the failure. To differentiate the fractured pin connections of the subs, the subs will be referred to as:


C1: Sub from Case 1


C2: Sub from Case 2


C3: Sub from Case 3


The fractures of all the pin connections were located in the last engaged threads of the pin connections. The last engaged threads of a connection experiences higher stresses and stress concentrations compared with the rest of the connection, making these threads susceptible to cracking. The as-received condition of the failed subs is presented in Figure 3. The C3 sub was received after initial metallurgical testing was performed by another lab. A portion of the sample that was used for previous testing was missing.

Figure 4: The fracture on the Case 1 sub showed a grainy texture and “chevron marks” that point toward the initiation site, which is typical morphology for brittle cracking.


The overall appearance of the fracture surfaces on the subs was flat and oriented perpendicular to the sub axis. The fracture on C1 and C2 exhibited a grainy texture and “chevron marks” that point toward the initiation site. This is typical morphology for brittle cracking (Figure 4).


The fracture on C3 exhibited a small fatigue region (approximately 5%) that was followed by brittle fracture. The fracture surface also had the grainy appearance (Figure 5). All three fracture surfaces present a minuscule shear lip, which is also typical of a brittle fracture. Note that the missing material was used for testing during previous investigation.


A thread profile analysis of the failed pin connections of C1 and C2 was performed to check for stretched threads, but no signs of such were observed. This gave further evidence that the pin connections on C1 and C2 failed in a brittle manner and not through ductile torsional/tensile overload.

Figure 5: The fracture on C3 exhibited a small fatigue region that was followed by brittle fracture. The fracture surface had a grainy appearance and presented a minuscule shear lip, which is also typical of a brittle fracture.


Material Testing


Material testing of the failed subs was performed to verify compliance with API Specification 7-1 and Standard DS-1 and to determine if improper material properties contributed to the failures. Tensile tests, chemical analysis and CVN tests were performed on the failed pin connection material of the subs.


Tensile strength and yield strength met the minimum requirements specified in API Specification 7-1 and Standard DS-1 for sub material. However, the CVN impact energy values did not meet the minimum requirements specified.


Typically, for the type of chemistry used, CVN values correlate well with fracture toughness. Low fracture toughness makes the material notch sensitive and typically results in predominately brittle fracture.


This indicates that the heat treatment processes were not performed properly to achieve the correct mechanical properties on the subs.


With temper embrittlement, generally, there is no detectable drop in expected yield strength, tensile strength and percent elongation of the material. A drop in the CVN values is often experienced.


In cases of extreme embrittlement, there may be a drop in the percent reduction of area. The material test results obtained on the failed subs are similar to test results commonly observed on components that have experienced temper embrittlement.


Because there is no major change in the tensile properties of the material, hardness testing cannot be used to detect temper embrittlement. Performing CVN tests followed by examination of the fracture surface of the CVN samples under a SEM are necessary to ascertain failure through temper embrittlement.

Figure 6: No signs of stretched threads were observed after a thread profile analysis of the failed pin connections of C1 and C2 was performed.


Scanning Electron Microscopy Analysis


The fracture surfaces of the failed pin connections on C1, C2 and C3 were electrolytically cleaned to remove oxides, which mask the fracture signatures. The cleaned fracture surfaces were then observed through a SEM. The fracture examination on C1 and C2 revealed features typical of transgranular fracture. The examination also revealed signatures of intergranular cracking (Figure 7).


The presence of both intergranular and transgranular features indicates a mixed mode fracture morphology. As discussed, the presence of intergranular cracking is often considered proof of failure induced through environmentally assisted cracking, such as SSC or hydrogen embrittlement. However, a saver sub is unlikely to come into contact with downhole corrosive environment.


Moreover, review of the operating conditions and environment provided no evidence of a source of nascent hydrogen. In this instance, presence of a mixed mode of intergranular and transgranular morphology on the fracture surface, combined with the low CVN values, indicates that the failure is more likely associated with temper embrittlement of the material resulting from improper heat treatment of the component.

Figure 7: The fracture examination using a SEM on C1 and C2 revealed features typical of transgranular fracture (left and middle) and signatures of intergranular cracking (left and right). The presence of both intergranular and transgranular features indicates a mixed-mode fracture morphology.


SEM analysis of C3 was also performed. However, no signatures were observed as the fracture surface was too corroded for examination.


To confirm if the subs underwent temper embrittlement, the fracture surface of the CVN impact test samples were analyzed under a SEM. Typically, examination of the fracture surface of CVN samples from a ductile material can present portions of ductile dimples and transgranular “cleavage” cracking.


This morphology is also expected on CVN samples that are machined from an inherently brittle material or a ductile material that has fractured through SSC or hydrogen embrittlement. The fracture examination of the CVN samples from the failed subs revealed mixed mode of intergranular, transgranular and some ductile dimple features (Figure 8).


This mixed mode of intergranular and transgranular cracking indicates that the subs likely underwent temper embrittlement resulting from improper heat treatment. Hence, presence of intergranular cracking does not confirm environmental cracking. Instead, CVN testing should be performed to check the fracture toughness of the material.


Additionally, the fracture surface of the CVN samples should be analyzed under a SEM to verify the fracture mode. Temper embrittlement of material is a strong possibility if the material presents low CVN values along with presence of intergranular or mixed mode of intergranular and transgranular cracking signatures on the fracture surface of the CVN sample.

Figure 8: The fracture examination of the CVN samples from the failed subs C1 (left), C2 (middle) and C3 (right) revealed mixed mode of intergranular, transgranular and some ductile dimple features. This indicates the subs likely underwent temper embrittlement resulting from improper heat treatment.


Guidelines on Alloying Elements


Temper embrittlement is often associated with the concentration of certain trace alloying elements, such as arsenic, antimony, tin and especially phosphorus. These minor impurities segregate along the austenitic grain boundaries during the tempering process and cause cracking along the grain boundaries.


Molybdenum, tungsten and zirconium greatly reduce embrittlement, and nickel, titanium and vanadium slightly reduce the temper embrittlement effects.


API Specification 7-1 and Standard DS-1 do not have any requirements for chemistry on subs. However, API Specification 5DP and Standard DS-1 have chemistry requirements for drill pipe tube and tool joints for phosphorus (0.020% max) and sulfur (0.015% max).


The sulfur content obtained on all the three failures was above the maximum allowed for drill pipe tube. The phosphorus obtained on C3 was above the maximum requirement, while the content for C1 and C2 was near the maximum allowed. This provides basis for strict control on these elements to minimize the possibility of temper embrittlement problems.


If not already required in the governing standard, supplementary requirements on content of phosphorus (0.02% max) and sulfur (0.015% max) should be specified when tubular components are ordered.


To check if the failure mechanism of the failed sub C1 was temper embrittlement, the sub material was re-heat treated. The re-heat treatment was also performed to confirm whether the sub was improperly heat-treated at the mill.


Sections of the failed pin connection were re-heat treated with the following conditions:


Condition 1: Temper at 657°C (1,215°F) for 45 min, and cool.


Condition 2: Austenitize at 872°C  (1,602°F) for 55 min; water quench; temper at 1,215°F (657°C) for 45 min; and cool.


The heat treatment procedures listed in the material test report (MTR) were used for re-heat treatment of the sub material. These conditions were chosen because the tempering temperature listed in the MTR does not fall in the temper embrittlement range.


If the sub was heat-treated at the mill with the conditions indicated in the MTR, temper embrittlement likely would not have occurred. After re-heat treating the sections from the failed pin connection with the conditions listed above, CVN impact tests were performed.


Significant improvement in the CVN values was observed from the re-heat treated material under both conditions. The reason for higher CVN values obtained through Condition 1 compared with Condition 2 is that the Condition 1 material underwent a double tempering process at the mill, and again during the re-heat treatment process.


The minimum and average impact energy of the re-heat treated sections was greater than the minimum required value specified in API Specification 7-1 and Standard DS-1. This confirmed that the failed sub was not heat-treated to the parameters listed in the MTRs.

Figure 9: To check if temper embrittlement still existed after re-heat treatment, the fracture surfaces of the CVN samples were analyzed under a SEM. Microvoid coalescence, seen as ductile dimples, was observed, which is indicative of ductile overload of the material.


To check if temper embrittlement still existed, the fracture surfaces of the re-heat treated CVN samples were analyzed under a SEM. Figure 9 present the fracture surfaces of the re-heat treated CVN samples as seen under SEM.


Microvoid coalescence (seen as ductile dimples) was observed on the fracture surface of the CVN sample, which is indicative of ductile overload of the material. No features of intergranular or mixed mode of intergranular and transgranular cracking were observed.


Hence, temper embrittlement was eliminated by performing the re-heat treatment on the failed sub material. Temper embrittlement was eliminated with only tempering the sub material (Condition 1). This confirms that temper embrittlement can be reversed with a tempering process performed at the appropriate temperature.


1. Detection of intergranular cracking morphology on fracture surfaces of a failed component is often considered to be confirmation of failure through SSC or hydrogen embrittlement, even when no evidence exists for exposure to H2S or a source of nascent hydrogen.


Study of intergranular cracking related failures has shown that intergranular fractures can occur not only when the component is exposed to corrosive environment, such as aqueous H2S, but can also be caused by temper embrittlement of the material resulting from improper heat treatment.


2. Temper embrittlement typically occurs when carbon or low-alloy steels are held at or slowly cooled through the temperature range of 375°C (705°F) to 575°C (1,065°F) during the tempering process.


3. Temper embrittlement is often associated with the concentration of certain trace alloying elements, such as arsenic, antimony, tin and especially phosphorus. These minor impurities segregate along the austenitic grain boundaries during the tempering process and cause cracking along the grain boundaries. If not already required in the governing standard, supplementary requirements on content of phosphorus (0.02% max) and sulfur (0.015% max) should be specified when tubular components are ordered.


4. The fracture surface of a failed component that has experienced temper embrittlement can present intergranular or mixed mode of intergranular and transgranular fracture morphology when analyzed under a SEM.


5. Generally, temper embrittlement of a material, does not lead to a detectable drop in expected yield strength, tensile strength and percent elongation of the material. However, a drop in the CVN impact energy values is often experienced, and in cases of extreme embrittlement, there may be a drop in the percent reduction of area.


6. Since there is no major change in the tensile properties of the material, hardness testing cannot be used to detect temper embrittlement of a material. Performing CVN tests followed by examination of the fracture surface of the CVN sample under a SEM are necessary to ascertain failure through temper embrittlement.


7. If the fracture surface on the failed components presents signatures of intergranular fracture, then it should not be presumed that the failure is associated with environmental cracking like SSC. Instead, CVN testing should be performed to check if the material has low impact energy values.


Once tested, SEM analysis of the fracture surface of the CVN sample must be performed to check for intergranular or mixed mode of intergranular and transgranular cracking. Presence of intergranular or a mixed mode of intergranular and transgranular morphology on the fracture surface of the CVN samples, combined with low CVN values, indicates a failure more likely associated with temper embrittlement of the material.


8. If the component being tested, such as tubing, does not have sufficient thickness to machine minimum required size CVN samples according to the governing API specification (minimum size accepted by API is 10 mm x 5 mm), then CVN samples should be machined to 10 mm x 2.5 mm (¼-in.) size to perform CVN testing.


Although the values obtained through testing cannot be compared against API specification requirements, the fracture surface of the CVN samples can still be analyzed under a SEM to check for intergranular or mixed mode of intergranular and transgranular cracking.


9. Temper embrittlement is a reversible process. Carbon and low-alloy steels that have experienced temper embrittlement can be restored to their original (or expected) toughness by heating (tempering) to 600°C (1,100°F) or above, followed by rapid cooling to below approximately 300°C (570°F). Material susceptibility to temper embrittlement can also be reduced by strict control and reduction of embrittling impurities, such as phosphorus.


This article is based on SPE/IADC 139762, “Intergranular Cracking of Oil Field Tubular Components Resulting from the Tempering Process,” SPE/IADC Drilling Conference & Exhibition, Amsterdam, The Netherlands, 1-3 March 2011.


References
1. API Specification 7-1, Specification for Rotary drill Stem Elements, first edition, American Petroleum Institute (March 2006),
Section 7.5, Page 26.
2. API Specification 5DP, Specification for Drillpipe, first edition, American Petroleum Institute (August 2009), Table C.4, Page 86.
3. Hill, T.H.: Drill String Design and Failure Prevention, T H Hill Associates, Inc. (September 2002).
4. Metals handbook, Volume 4, Heat treating, ninth edition, American society for metals (November 1981), Page 84.
5. Metals handbook, Volume 11, Heat treating, ninth edition, American society for metals (November 1981), Page 6, 11, 99.
6. Metals handbook, Volume 12, Heat treating, ninth edition, American society for metals (November 1981), Page 13, 174.
7. Standard DS-1® Volume 1: Drilling Tubular Product Specification, third edition, fourth printing, T H Hill Associates, Inc. (January
2004), Table 3.2.1, Page 20 and Table 3.1, Page 13.
8. William T. Becker. ASM International Course 0335, Principles of Failure Analysis, Lesson 3: Ductile and Brittle Fracture, Page
61, 62, 63.


View the original article here

Study simulates kick responses during MPD

Experimental wells confirm alternative well control procedures to be effective in range of well conditions


By J.E. Chirinos, J.R. Smith, D.A. Bourgoyne, Louisiana State University

Figure 1 shows the layout for experimental well LSU #2, where a gas kick was emulated by injecting gas in the 1 ¼-in. tubing until a desired pit gain was obtained. The well was used to evaluate two non-circulating kick responses and the pump startup procedure for kick circulation after a non-circulating response is applied. A computer simulation approach was also used to evaluate and confirm the applicability of these procedures.


According to IADC, managed pressure drilling (MPD) is defined as “an adaptive drilling process used to precisely control the annular pressure profile throughout the wellbore.” The technology uses different approaches to control and influence wellbore pressure. It is able to actively manipulate the wellbore pressure profile by controlling backpressure, drilling fluid proprieties and circulating friction; hence, a combination of tools is used to achieve MPD objectives to reduce nonproductive time (NPT) and mitigate drilling hazards.


MPD has been shown to be successful in wells where kicks, lost returns, ballooning, wellbore instability and/or differential sticking cause excessive NPT or inability to reach objectives using conventional drilling methods.


Although the main application of MPD has primarily been drilling in a narrow margin between pore pressure and fracture pressure, it’s increasingly realized that MPD can be applied anywhere where more precise control of wellbore pressure is an advantage. As a result, the industry has addressed a significant number of challenges by using MPD. Applications include: narrow drilling margin between pore pressure and fracture pressure, depleted formations, tight-gas sands, shallow gas hazards, wellbore stability problems, fractured carbonates, HPHT wells, H2S wells, slim-hole coiled-tubing drilling and casing drilling.


This article focuses on one variation of MPD – constant bottomhole pressure (CBHP) – which uses a combination of equipment to manipulate annular frictional pressure losses and casing pressure to keep wellbore pressure at a selected depth relatively constant. Although the CBHP method of MPD has better control of wellbore pressure while drilling, well control events can still occur because of uncertainty related to pore pressure and fracture pressure, human error or equipment failure.

Table 1 (left) provides an example pump startup schedule for routine operations. It steadily increases the pump rate to keep BHP approximately constant. CP* = desired casing pressure for routine operations. Table 2 (right): The post-kick pump startup schedule for MPD kick circulation is based on a stabilized shut-in casing pressure (SICP) and the routine pump startup ?P.


Several alternative well control procedures during the application of the CBHP method have been studied by industry-supported research to establish a basis for determining appropriate procedures. This research has defined two non-circulating responses as preferable among multiple alternative non-circulating responses. These two responses are described as a simple shut-in and as a MPD pump shutdown with a “choked flow check.” Both require a pump startup schedule to begin circulating out a kick. The goal of this article is to explain and document these procedures and to demonstrate by applying them in computer simulations and to gas kicks taken in a full-scale experimental well.


The CBHP method is the most common variation of MPD. During its application, annular pressure in the well is held constant or near constant at a selected depth. CBHP actively controls the surface pressure using a drilling choke to compensate for changes in frictional pressure losses (?PAF) during routine operations, such as making a connection.


An important characteristic of this method of MPD is the minimization of wellbore pressure variation to keep wellbore pressure within the drilling margin. Consequently, it allows drilling within a narrower window, or margin, between fracture and pore pressures than conventional drilling methods.


CBHP uses a collection of tools to control wellbore pressure during drilling operation. The minimum equipment required to apply CBHP are a rotating control device (RCD), a drilling choke manifold and, typically, a non-return valve. The RCD keeps annular space closed and diverts flow to the drilling choke; it is equipped with a rotating packer that rotates and holds pressure in the well during drilling operations.


The drilling choke manifold helps manipulate and control surface pressure while drilling; it can be controlled manually, semi-automatically or automatically. A non-return valve or float valve is installed in the bottomhole assembly; it allows only downward flow of drilling fluids, which is necessary if the well will be statically underbalanced.


Other optional tools can complement CBHP operation to improve wellbore pressure management, such as coriolis meters (flow meter), continuous circulating systems, downhole deployment valves, backpressure pumps, surface multiphase separators, pressure-while-drilling tools (PWD) and hydraulic flow modeling.


Pump Shutdown, Pump Startup Schedule


Many authors have discussed the method used to transition from dynamic to static state during CBHP. Medley, et al, and Rehm, et al, described a method to achieve CBHP objectives when rig pumps are shut down. It relies on a hydraulic model to estimate annular friction losses and equivalent circulating density (ECD) at different pump rates. Then, the ECD is manipulated by adjusting the casing pressure to keep wellbore pressure constant when the pump rate is reduced.


Wellbore pressure and ECD estimates are made with hydraulic models and can be validated with PWD tools. For example, to make a connection, the choke opening is reduced to increase casing pressure to the desired pressure, then the pump rate is reduced. Thus, surface pressure increases as the frictional pressure loss decreases by an equal amount. This process continues stepwise until the annulus surface pressure is at the maximum calculated value and the pumps are stopped.


The final annulus surface pressure should be equal to the frictional annulus pressure losses in the well, plus any surface backpressure held during normal operations.

Table 3 defines the pump startup and pump shutdown schedule for normal conditions, and Figure 2 illustrates application of the schedule in well LSU #2. BHP was kept essentially constant during pump startup and shutdown.


Initial Responses during Well Control Operation


A few studies have been done in the area of initial responses to well control events for the CBHP method of MPD. Das (2007) documented the first research from the university-industry consortium related to initial responses to a kick taken during the CBHP method. He compared three initial responses by using computer simulation: shutting in the well conventionally, increasing choke pressure while keeping the same pump rate, and increasing pump rate while keeping choke pressure constant. The most important conclusions from this research were: a) no single response was identified as the best, b) circulating responses may stop the influx faster than non-circulating responses, and c) the increased choke pressure response leads to a lower shoe pressure than shut-in, thus it reduces the risk of lost returns at the shoe.


In 2009, Guner studied the most appropriate initial response and kick circulation method for an unexpected reduction of bottomhole pressure created by a surface equipment failure or unintended ECD reduction. The conclusions explained that shut-in was the initial response that is applicable for all kick scenarios; however, increasing choke pressure would generally be the most effective response when it was practical. For both responses, Guner recommended kick circulation at the normal drilling circulation rate.


In 2009, Davoudi documented a comprehensive investigation of alternative initial responses to gas kicks taken during drilling operations with the CBHP method. He studied nine responses, five of them non-circulating and four circulating responses. They were compared based on the ability to stop formation flow, minimizing the risk of lost returns and additional kick influx, and the reduction of pressure imposed at surface and the casing shoe.


Davoudi performed more than 150 simulations and found that no single best initial response to all kicks could be identified. However, three initial responses were demonstrated to have a broad application to different kick scenarios: a rapid increase of casing pressure until flow out equals flow in, a simple shut-in, and an adaptation of the MPD pump shutdown schedule that allowed confirmation of low rate kicks using a choked flow check. In addition, he concluded that the best initial response depended on well conditions and the equipment being used.


Based on the consortium research, Davoudi, et al (2010) presented a proposed approach for selecting initial responses during well control events for the CBHP method. They explained that one criteria in selecting the initial kick reaction must be the equipment available onsite, specifically whether flow-out metering was being used.


In addition, according to this approach, the selection of the initial response should consider the certainty of the well control event. Each initial response has key factors that need be considered to ensure applicability and efficiency during the well control operations.

Figure 3: Actual shut-in pressures in LSU #2 were recorded, with the stabilized SICP interpreted at 510 psi. Table 4: A post-kick pump startup schedule for the experimental well was made based on the schedule for normal conditions.


Research Method


This article focuses on evaluating proposed procedures for the two non-circulating kick responses described by Davoudi in 2010 and on the pump startup procedure for kick circulation after a non-circulating response is applied. Two approaches were used to evaluate and confirm the applicability of these procedures: computer simulations and full-scale experiments.


Non-Circulating Responses


Simple Shut in


This response is widely known and accepted in conventional operations. However, according to work by Gunner in 2009, the simple shut-in procedure can be applied in MPD operation where accurate flow metering is not available or where equipment failure endangers the operation. This procedure can be summarized as:


1. Stop drilling, i.e., pick up off bottom and stop rotating.


2. Shut down the pumps as quickly as practical.


3. Close the drilling choke as quickly as practical.


4. Record shut-in casing pressure (SICP) versus time.

Figure 4: In this plot of actual and simulation results for a simple shut-in and pump startup after the kick, Number 1 represents the moment when the valve from the gas source was opened to LSU #2, and BHP increased by more than 500 psi. Number 2 shows pressure in the gas source is reduced as gas was injected into LSU #2.


MPD Pump Shutdown with Choked Flow Check and Shut-in


This method is based on the pump shutdown schedule for routine operations in CBHP. It can be used to check for flow when signals of a kick are not clear. The procedure can be outlined as:


1. Stop drilling, i.e., pick up off bottom and stop rotating.


2. Apply the regular pump shutdown schedule.


3. At the end of the schedule, attempt to hold the casing pressure constant for approximately two minutes by adjusting the drilling choke.


4. If it is necessary to bleed fluid from the well to maintain a constant casing pressure, shut in the well by closing the drilling choke and record SICP versus time.


5. If not (i.e., if the casing pressure does not increase above the final schedule pressure with the choke closed), resume drilling operations but continue monitoring for kick warning signs.


The application of these non-circulating responses is dependent on the RCD static pressure rating. If the expected shut-in casing pressure will exceed the RCD rating, close the annular preventer or pipe rams and open the choke line valve with the well control choke closed rather than closing the drilling choke.


Pump Startup Schedule after a Non-circulating Response to a Kick


Pump startup and pump shutdown procedures are routine MPD operations that are intended to keep wellbore pressure relatively constant during pump manipulations. When a non-circulating response is applied, a new pump startup schedule to start kick circulation is needed. This procedure should keep BHP relatively constant and above formation pressure.


The goal of this part of the research was to document and evaluate a simple method to start the kick circulation and keep bottomhole pressure constant after a non-circulating response. The method uses information available on the rig to define a pump startup schedule.


The proposed procedure is:


1. A routine pump startup schedule should already exist. Table 1 shows an example of a pump startup schedule with four steps of increasing pump rate, Q1 to Q4. As can be seen from the table, when the mud pumps are off, the casing pressure (CP) is equal to the annular friction pressure loss (?PAF) plus a desired casing pressure for routine operations (CP*). Notice that during the startup, CP is reduced by a constant pressure increment (?P) at each step until it is equal to the CP*.


This schedule keeps BHP approximately constant while the mud pump rate is increased. Note that a pump shutdown would use this same schedule beginning at Q4 and reducing the pump rate.


2. Once a potential kick has been recognized and the relevant non-circulating response applied, is recorded until a stabilized SICP can be interpreted.


3. Based on the stabilized SICP and the routine pump startup ?P defined in step 1, a post-kick pump startup schedule is defined for the MPD kick circulation. Table 2 illustrates a post-kick pump startup schedule equivalent to the routine schedule in Table 1. CP0 is selected as equal to SICP plus a desired safety overbalance factor (?POB). At each step in the schedule, the CP is reduced by the same ?P, and the flow rate is increased to the same Q as defined for the routine pump startup.


4. Once the post kick pump startup schedule has been applied, the pump rate stabilized at Q4 and the choke pressure stabilized at CP0 Kick – 4?P, the drill pipe pressure should also stabilize. The kick is then circulated out, keeping drill pipe pressure constant at that value and the pump rate constant at Q4, equivalent to the driller’s method of well control.

Figure 5: In the method of MPD pump shutdown with choked flow check and shut-in, although the casing pressure time response did not match exactly between simulation and experiment, the trends and magnitude of response to choke manipulation are similar.


Well Scenarios for Evaluating Procedures


LSU #2 is a 5,884-ft deep vertical well with 9 5/8-in. casing. Most of the full-scale results of this research were measured in and then compared with computer simulations of LSU #2. Two additional well geometries were used to perform simulations representative of other drilling environments suitable for MPD application: Well X is a 6-in. slim-hole directional well with a potential deep kick zone whereas Well Y is 12 ¼-in. straight hole with a potential high-pressure sand at the bottom.


Simulation Procedure


The computer simulations start during drilling operations just above the high-pressure sands in wells X and Y. For LSU well #2, a high-pressure sand was created in the simulator to emulate real conditions. The bit would drill into the high pressures, where a gas kick would be taken. Two initial responses were used to stop formation flow: simple shut-in and manual MPD pump shutdown with a choked flow check. If a simple shut-in response was used, the pumps were shut down, and then the choke was closed as fast as practical. However, if a manual MPD pump shutdown with choked flow check was performed, the pump shutdown schedule for routine operations was applied.


At the end of the schedule, the casing pressure that was required to compensate for the lost annular friction (?PAF) was held constant for approximately two minutes before shutting the well in, unless shutting in was required to maintain casing pressure. In both cases, SICP was recorded and used to create a pump startup schedule for kick circulation. All simulations were carried out until the gas was circulated completely out of the system; the data was recorded and analyzed using a spreadsheet.


Experimental Procedure


In the experimental well LSU #2, drilling fluid was circulated down the annulus between the 3 ½-in. and 1 ¼-in. tubing at the desired pump rate, and the flow returns were taken through 3 ½-in. by 9 5/8-in. annulus. The gas kick was emulated by injecting gas in the 1 ¼-in. tubing until the desired pit gain was obtained. Subsequently, the planned initial response was applied to stop formation flow and circulate out the kick. The influx was circulated out through a mud-gas separator, where the gas was directed to the flare and the drilling fluid was returned to the mud pits.


During the experiments, the drill pipe, casing and gas-injection pressures at the surface were continuously monitored and recorded, and subsequently analyzed.


Pump Startup, Shutdown for Routine Operations


The method described was tested in a full-scale experiment in the LSU #2 well. The drilling fluid used in the experiment was water, and the kick fluid was natural gas. A restricted valve was used in a surface return line to simulate higher annulus frictional pressure losses. Conventional detection for kicks was used in this experiment. The pump startup and pump shutdown schedule for normal conditions is detailed in Table 3, and Figure 2 shows its application. Solid lines represent data from the actual well, and dashed lines correspond with data for the equivalent computer simulation. Notice that BHP was kept essentially constant during pump startup and pump shutdown.


Simple Shut-in and Pump Startup after the Kick


The full-scale experiment was performed according to the procedure explained above. Gas was injected into the well until a 10-bbl kick was recognized. Then the well was shut in, and SICP was recorded vs time. The initial circulating underbalance was approximately 240 psi. Figure 3 shows shut-in drill pipe (a non-return valve was not used) and casing pressure buildup; the stabilized SICP was interpreted to be 510 psi.


Table 4 illustrates the post-kick pump startup schedule based on the pump startup for normal conditions in Table 3 and the SICP. In this experiment, ?POB was assumed to be equal to zero.


Once the post-kick pump startup schedule was prepared, it was applied manually by two persons: one operated the pump and the other manipulated the choke to control casing pressure. Figure 4 shows the experimental results.


It can be observed from the graph that BHP was kept almost constant during the post-kick pump startup, which achieves the goal described in previous section. Notice that the drill pipe and bottomhole pressure results from the experiment (solid lines) and the simulation (dash lines) are not identical for this case, probably because it was difficult to get exactly the same casing pressure versus time in the simulation as in reality.


However, the similarity in behavior supports the relevance of using simulations for this study. In the plot, number 1 represents the moment when the valve from the gas source (a well that is essentially a gas storage bottle) was opened to the LSU #2 well; notice that BHP increased more than 500 psi. Number 2 in the plot shows how the pressure in the gas-storage well is reduced as the gas is injected into the LSU #2 well to simulate the gas kick. BHP was controlled when the shut-in procedure was applied.


MPD Pump ShutDown with Choked Flow Check, Shut-in


The second non-circulating response was applied to a low feed-in rate kick. The gas-storage well pressure was set to cause a 100-psi underbalance in LSU #2. A restricted flow path from the storage well was opened, a slight increase in return flow was detected as an indication of a possible kick, and the manual MPD pump shutdown with choked flow check was applied.


Figure 5 shows the experimental results. It can be seen that the pump shutdown schedule described in Table 3 was applied to keep BHP constant. The choked flow check was extended over a period of about five minutes to show that the choke had to be opened periodically to maintain the intended casing pressure at the end of the MPD shutdown schedule.


When the choke was subsequently closed, the casing pressure would build back up, indicating that the well had been underbalanced. The experimental results from the test well were also compared with a computer simulation for the same conditions, shown in the dashed lines. Although the time response of casing pressure in the simulation is not an exact match to experiment, both the trends and the magnitude of the response to choke manipulation are similar.

A pump startup schedule (Table 5) was defined for Well X to keep BHP constant during pump manipulations; the schedule is simulated in Figure 6.


Example Simulations of Shut-in and Pump Startup


Simulations were conducted to provide a basis for evaluating the application of pump startup schedules to a wide range of well conditions. This section describes an example of these simulations.


A pump startup schedule was defined to keep BHP constant during pump manipulations (Table 5) for Well X. Figure 6 shows the simulation of the pump startup and pump shutdown for routine operations for the well. It can be seen that BHP is kept almost constant while the pump is being started and shut down.


Notice that casing pressure is used to compensate the loss of friction in the well; it is increased when pump rate is reduced, and it is reduced when pump rate is increased.


Once the pump startup schedule for routine operations was defined, the kick simulation was run according to the procedure described in an earlier section. The well was drilled into a high-pressure sand with a circulating underbalance of 0.2 ppg. As a result, a 20-bbl kick was taken, the well was shut in, and SICP was recorded.


Based on the pump startup schedule for routine operations (Table 5) and the SICP, a new pump startup schedule (Table 6) for kick circulation was built, and the kick was circulated out successfully. The stabilized SICP was equal to 1,183 psi. A safety overbalance (?POB) of 100 psi was added to the SICP for determining the post-kick startup schedule.


Figure 7 shows the simulation results for this scenario. A kick was recognized by the increase of surface mud flow rate out (Qout) and pit gain, as shown by the red line and the green line respectively. Drilling was stopped, the mud pump was shut down, and the choke was closed with a pit gain of about 20 bbls. Casing pressure subsequently increased to balance the kick zone’s pressure at SICP = 1,183 psi. Hence, the BHP increased and stopped formation flow.


At this point, the post-kick pump startup schedule was prepared and applied. Figure 6 demonstrates how casing pressure (purple line) was decreased while pump rate (blue line) was increased according to the schedule in Table 6. Notice that BHP (light blue line) was kept almost constant during the application of this schedule.


Three well scenarios, LSU #2, Well X and Well Y, representing hole sizes from 6 in. to 12.25 in. were simulated. Kicks were simulated in each well configuration for total pit gains of 2, 10 and 20 bbl and for three levels of circulating underbalance. All simulations were run successfully and demonstrated that BHP was kept relatively constant using the proposed post-kick pump startup schedule and procedure.

Table 6: A pump startup schedule for kick circulation in Well X was built. Figure 7 shows the simulation results of shut-in and pump startup for Well X.


Conclusions


• Simple shut-in is a procedure that can be applied during MPD operations to stop formation flow. Previous work has shown that it is the preferred response to a kick if accurate flow-out metering is not available or if a circulating response is impractical due to an equipment failure. Simple shut-in can be applied rapidly, typically in less than one minute, and it can provide a SICP as a basis for a pump startup schedule.


• The MPD pump shutdown with choked flow check response allows checking for flow during MPD operations without letting bottomhole pressure drop significantly below the intended pressure. Consequently, this response can be used to detect or confirm, and then shut in, low feed-in rate kicks that cannot be detected conclusively during circulation.


• The pump startup schedule method described successfully maintains bottomhole pressure relatively constant during pump startups for kick circulation. It is applicable after all non-circulating responses.


• Applicability of these methods was confirmed with both full-scale experiments and simulations covering a wide range of well conditions.


This article is based on IADC/SPE 143094, “Alternative Shut-In and Pump Start-Up Procedures for Kicks Taken During MPD Operations,” IADC/SPE Managed Pressure Drilling and Underbalanced Operations Conference & Exhibition, 5-6 April 2011, Denver, Colo.


Acknowledgements


The authors wish to acknowledge all of the previous researchers of the MPD consortium, especially Majid Davoudi who completed the study of the best initial responses to kicks taken in MPD operations, his contribution was essential to the conclusions reached in this work and are very much appreciated.


We thank SPT Group for providing licenses and technical support for the Ubitts and Dynaflodrill simulators, which were used extensively for this study. We also thank the consortium members: Chevron Energy Technology Corporation, Total E & P, ConocoPhillips, Shell E & P Company (SEPCO), At Balance™, Secure Drilling™, and Blade Energy Partners for their financial and technical support for this research. Note that their participation in the consortium does not indicate endorsement of this work or the conclusions reached.


Finally, we thank the faculty and staff of the Craft and Hawkins Department of Petroleum Engineering, especially PERTT Lab personnel, for their assistance in this research.


References


Arnone, M. A., and Vieira, P. 2009. “Drilling Wells With Narrow Operating Windows Applying the MPD Constant Bottom Hole Pressure Technology—How Much the Temperature and Pressure Affects the Operation’s Design”. Paper SPE/IADC 119882 presented at the SPE/IADC Drilling Conference and Exhibition, Amsterdam, The Netherlands, 03/17/2009. doi: 10.2118/119882-MS.


Das, A. K., Smith, J. R., and Frink, P. J. 2008. “Simulations Comparing Different Initial Responses to Kicks Taken During Managed Pressure Drilling”. Paper IADC/SPE 112761-MS presented at the IADC/SPE Drilling Conference, Orlando, Florida, USA, 03/04/2008. doi: 10.2118/112761-MS.


Das, Asis Kumar. 2007. Simulation study evaluating alternative initial responses to formation fluid influx during managed pressure drilling. MS Thesis, Craft & Hawkins Department of Petroleum Engineering, Louisiana State University, Baton Rouge, LA.


Davoudi, M., Smith, J. R., Patel, B. M., and Chirinos, J.E. 2010. “Evaluation of Alternative Initial Responses to Kicks Taken during Managed Pressure Drilling”. Paper IADC/SPE 128424 presented at the IADC/SPE Drilling Conference and Exhibition, New Orleans, LA, USA, 2-4 February. doi: 10.2118/128424-MS.


Davoudi, Majid. 2009. A Simulation-based evaluation of Alternative Initial Responses to Gas Kicks During Managed Pressure Drilling Operations. MS Thesis, Craft & Hawkins Department of Petroleum Engineering, Louisiana State University, Baton Rouge.


Guner, H. 2009. Simulation Study of Emerging Well Control Methods for Influxes Caused by Bottomhole Pressure Fluctuations during Managed Pressure Drilling. MS Thesis, Craft & Hawkins Department of Petroleum Engineering, Louisiana State University, Baton Rouge.


Hannegan, Don M. 2006. “Case Studies–Offshore Managed Pressure Drilling”. Paper SPE 101855 presented at the SPE Annual Technical Conference and Exhibition, San Antonio, Texas, USA. doi: 10.2118/101855-MS.


IADC. 2009. Glossary of MPD and UBD 2009. Available on http://www.iadc.org.


Malloy, K. P., Stone, R., Medley, G. Harold, Hannegan, D. M., Coker, Ol. D., Reitsma, D., Santos, H., Kinder, J., Eck-Olsen, J., McCaskill, J. Walton, May, J., Smith, K. L, and Sonnemann, P. 2009. “Managed-Pressure Drilling: What It Is and What It Is Not”. Paper IADC/SPE 12228 presented at the IADC/SPE Managed Pressure Drilling and Underbalanced Operations Conference & Exhibition, San Antonio, Texas, 02/12/2009. doi: 10.2118/122281-MS.


Malloy, Kenneth P. 2008. A Probabilistic Approach to Risk Assessment of Managed Pressure Drilling in Offshore Applications. Joint Industry Project DEA155: U.S Department of the Interior Minerals Management Service.


Medley, G., Moore, D., and Nauduri, A.S. 2008. “Simplifying MPD – Lessons Learned”. Paper SPE/IADC 113689-MS presented at the SPE/IADC Managed Pressure Drilling and Underbalanced Operations Conference and Exhibition, Abu Dhabi, UAE, 01/28/2008. doi: 10.2118/113689-MS.


Rehm, Bill. 2009. Managed pressure drilling, Gulf drilling series. Houston, TX: Gulf Pub.


View the original article here